Boeckman Road provides a vital connection through Wilsonville as one of three primary east/west corridors for travel. With new Wilsonville neighborhoods in the Frog Pond area and a new primary school on the way, the road is even more essential.
The Boeckman Road Corridor Project provides upgrades on Boeckman Road between Canyon Creek Road and Wilsonville/Stafford Roads to make it safer and easier for all users—drivers, cyclists, pedestrians, and riders—along the corridor.
To minimize disruptions, speed up completion, and provide cost efficiencies, the project combines four projects in one.
Learn more at ci.wilsonville.or.us/boeckman. And check the tabs below for opportunities to learn more about the project and engage with the project team about the project, the timeline, its impacts and the results.
Boeckman Road provides a vital connection through Wilsonville as one of three primary east/west corridors for travel. With new Wilsonville neighborhoods in the Frog Pond area and a new primary school on the way, the road is even more essential.
The Boeckman Road Corridor Project provides upgrades on Boeckman Road between Canyon Creek Road and Wilsonville/Stafford Roads to make it safer and easier for all users—drivers, cyclists, pedestrians, and riders—along the corridor.
To minimize disruptions, speed up completion, and provide cost efficiencies, the project combines four projects in one.
Learn more at ci.wilsonville.or.us/boeckman. And check the tabs below for opportunities to learn more about the project and engage with the project team about the project, the timeline, its impacts and the results.
Boeckman Road Corridor Improvements has finished this stage
In April '21, the Council approved staff's recommendation to build a bridge over the "Boeckman Dip" and fund additional road improvements.
Contractor Selection
Boeckman Road Corridor Improvements has finished this stage
In June '22, the Council approved anagreement with Tapani | Sundt A Joint Venture to advance inter-connected projects along the Boeckman Road Corridor.
Environmental & Geological Assessments and Surveys
Boeckman Road Corridor Improvements has finished this stage
Work is taking place in summer of 2022.
Project Design + Outreach
Boeckman Road Corridor Improvements has finished this stage
Design and outreach activities begin in summer '22 and continue until summer '23, when construction is scheduled to begin.
Construction
Boeckman Road Corridor Improvements is currently at this stage
Construction is scheduled to begin in summer '23. For a large portion of the project, a segment of Boeckman Road is to be closed to the public. Construction is set to be completed in fall '24.